For procurement, project managers and factory leaders

Robot Cell SAT Checklist: Evidence to Verify On Site

Turn a factory-tested configuration into a controlled site handover with test conditions, evidence and named owners.

Engineers reviewing acceptance documents outside a guarded stationary robot cell

Five records that make SAT executable

Give every test an identity and a release decision. A checked box without a result cannot explain what was accepted.

Baseline
Robot, tooling, controller, PLC, HMI and safety configuration revisions.
Preconditions
Site readiness, approved test method, competent personnel and controlled access.
Acceptance criteria
Contract requirement, test parts, operating conditions and expected result.
Evidence
Measured result, record reference, date, operator and witness.
Disposition
Accepted, hold or agreed restricted release; owner, due date and re-test.

A commercial signature cannot replace unresolved safety validation. Record the exact permitted operating boundary and keep blocking issues closed to production until the responsible team verifies corrective action.

What SAT adds after FAT

Factory acceptance testing checks the agreed configuration before shipment. Site acceptance testing checks that configuration after installation, with the production site's utilities, connected machines and environmental conditions. OSHA explicitly describes SAT in this site-dependent context. Use the FAT report as a starting record: identify tests carried forward, tests to repeat and tests that could only be performed on site. Keep the FAT defect log and configuration changes attached so that a changed cable route or software revision does not silently inherit an earlier pass.

Separate installation completion, safety validation, process acceptance and production release. They answer different questions. A cell can be physically assembled while utilities remain unstable; it can execute motion while quality evidence remains incomplete. Define who approves each gate and which records are required. ISO 10218-2 covers integration and information for use across the application lifecycle; its public scope is not a substitute for the applicable project standard or a certificate of compliance.

Further reading: OSHA — Industrial Robot Systems and System Safety ↗ · ISO — ISO 10218-2:2025 integration and lifecycle scope ↗

Carry forward, repeat or add: three SAT evidence routes

01FAT evidence retained

Unchanged configuration; identify the original record and justify applicability.

02Site-dependent re-test

Installation, utilities, safeguards and connected equipment affect the result.

03Project-specific acceptance

Real material flow, production conditions, quality and handover criteria.

Control interface review beside a guarded robot and conveyor

Confirm the site before beginning acceptance trials

Compare delivered model and serial identities with the purchase baseline. Check transport damage, anchoring and leveling records, tooling location, peripheral equipment and installed software versions. Record utilities at the agreed connection points under the agreed operating conditions: supply characteristics, air, cooling, gases, extraction and network access where relevant. Do not use universal utility thresholds; obtain them from the installed equipment documents and project design. Assign missing facility work to its owner before it becomes a failed process test.

For each machine or conveyor interface, record signal meaning, source, destination, permissives, timeout behavior and reset ownership. Verify normal transitions and approved abnormal conditions. A network connection or illuminated ready bit is insufficient if the two devices interpret that bit differently. Record time-stamped state evidence and the corresponding PLC/robot program revision, then preserve the final interface map with the handover package.

Utility connections and air regulator for a robot cell readiness review

Test safety, production and recovery as separate evidence sets

The responsible safety specialists should use the approved validation plan for the installed application, including guarding, interlocks, protective stops, emergency functions, operating modes and reset behavior. Plan tests without exposing people to hazardous motion or improvising faults. A3's September 2026 safety update highlights interactions during maintenance and troubleshooting as well as normal production. Capture the validated settings and records; any subsequent relevant change needs an assessed verification scope.

Production trials should use agreed part families, incoming variation, operators, consumables and measurement methods. Measure the full cycle, including loading, clamping, transfer, process, inspection and unloading. Define sample quantity, duration, exclusions, quality limits and handling of interruptions in the protocol rather than inventing them during the witness test. Record rejected parts and rework alongside good output. Approved recovery scenarios should verify part disposition, retained state and restart permissions after interruption; successful restart alone does not prove the interrupted part is acceptable.

Further reading: A3 — The State of Industrial Robot Safety (22 September 2026) ↗

From site readiness to signed SAT

01Freeze

Protocol, revisions and witnesses

02Prepare

Installation and utility readiness

03Validate

Approved safety and interface tests

04Demonstrate

Cycle, quality and recovery evidence

05Handover

Close blockers, documents and ownership

Technical binder, teach pendant and backup device for robot cell handover

Close issues with evidence and a usable handover pack

Training should identify operator, programmer and maintenance tasks, language, attendees and demonstrated competence for the agreed scope. Hand over as-built mechanical and electrical drawings, manuals, safety records, interface definitions, program manifests, parameter sets, license records and access arrangements. Check that backups can be restored using the agreed procedure in a controlled environment, with any motion-related validation managed separately. A saved file is not yet evidence of a usable recovery package.

Use an open-item register with requirement, observed deviation, operational effect, corrective action, accountable owner, date and re-test evidence. Keep safe-use blockers separate from cosmetic or documentation issues. Any agreed restricted release must identify its exact scope and approval authority; it cannot erase unresolved hazards. Link the signed SAT decision to the final configuration and service contacts so that operations inherits both the accepted system and the remaining responsibilities.

Copyable robot cell SAT evidence table

Add requirement ID, protocol revision, actual observation, evidence filename, witness, date and disposition to each row. The method column describes planning inputs; the signed project protocol sets the test and passing criteria.

Copy the rows into your RFQ or investment worksheet.

Acceptance itemFAT record to carrySAT method / site inputEvidence and accountable owner
Delivered configurationBOM and serial manifestMatch installed equipment and revisionsAs-built manifest; supplier and buyer
InstallationApproved layout and mountsCheck damage, anchoring and accessInstallation record; site/integrator
UtilitiesEquipment requirementsRecord actual supply at test conditionsUtility measurements; facility owner
Machine interfacesSignal and state mapWitness handshakes, permissives and timeoutsState log; controls owners
Safety functionsDesign and validation baselineExecute approved installed-application validationValidation report; competent safety team
Operating modesMode and access specificationVerify selection, permissions and transitionsMode test record; integrator/user
Complete cycleFAT part and cycle conditionsUse agreed site mix and full-cycle definitionTime and interruption log; process owner
QualityDrawing and process criteriaMeasure samples using approved methodTraceable measurement record; quality owner
Abnormal recoveryApproved recovery scenariosVerify part disposition and restart stateRecovery results; controls/process owners
TrainingAgreed task syllabusDemonstrate tasks with designated staffAttendance and task evidence; user/supplier
Technical documentsDeliverable indexCheck final as-built revisions and languageDocument register; document owner
Backup and licensesProgram/software manifestControlled restore procedure and access checkRestore record; authorized controls team
Open items and handoverFAT issue historyClose blockers and assign remaining actionsSigned decision and owners; buyer/integrator

Frequently asked questions

Does a passed FAT remove the need for SAT?

No. SAT verifies site utilities, installed interfaces and application conditions that may differ from the factory test. Carry forward valid FAT evidence and document what must be repeated or added.

How many cycles should SAT include?

There is no universal number. Agree duration, part mix, sample quantity, cycle definition, interruptions and quality criteria in the project protocol before testing.

Who should execute and witness SAT?

Assign the integrator, site utility owners, process and quality teams, competent safety specialists and buyer witnesses by test scope. Record execution and approval roles separately.

Can a cell be handed over with open items?

Only within an explicitly agreed release boundary with owners and closure evidence. Unresolved safe-use blockers require corrective action and verified closure before affected production use.

Sources for the planning framework

  1. OSHA — Industrial Robot Systems and System Safety ↗
  2. ISO — ISO 10218-2:2025 integration and lifecycle scope ↗
  3. A3 — The State of Industrial Robot Safety (22 September 2026) ↗

Define the site acceptance boundary before delivery

Send the application, configuration baseline, FAT record, site interfaces and acceptance requirements. TubeFrame can coordinate project inputs and delivery responsibilities for a reviewable SAT scope.

Discuss robot cell acceptance ↗
Request a QuoteWhatsApp